The process of undergrounding involves three key steps: planning, permitting and easements, followed by construction.
Photo Credit: Taylor Hillo
Obtaining permits from county, state and environmental agencies is often the longest part of undergrounding before construction can begin.
Photo Credit: Taylor Hillo
Concrete vaults will house the underground power lines and serve as access points for maintenance.
Crews Make Undergrounding Progress in Burn Scar
Southern California Edison crews are close to completing over a mile of undergrounding through an Altadena neighborhood.
Taylor Hillo
ENERGIZED by Edison Writer
Contributors
Photo Credit: Taylor Hillo
Video Credit: Taylor Hillo, Roberto Lazarte
SCE Expedites Undergrounding in Fire-Damaged Communities
After windstorm-driven fires erupted throughout SoCal, Southern California Edison crews have been working tirelessly to rebuild the electrical system with a mission of building ...
In-Person Help Available for SCE Customers in Altadena
As members of Southern California Edison customer support team, Daniel Cortez and Armando Rangel usually help answer questions over the phone, but at the Altadena Disaster ...
Creating New Underground Paths for Power Lines
Nearly 12 feet underground and spread across two miles in Riverside County sit six concrete vaults that will house Southern California Edison electrical equipment and ...